Positive train control could have prevented Amtrak derailment, but it’s not quite on track

The technical aspects of these systems can vary, but they generally include a positioning system on each train and information on rules for sections of track, such as speed restrictions. There also has to be a way of communicating these data throughout the network. For example, PTC would override manual control if it sensed that the train was entering a section of track at double the posted speed limit.

The potential safety benefits
Interest in PTC dates back to at least 1990, when the NTSB first placed it on its “Most Wanted List of Transportation Safety Improvements” where it is still regularly featured up to the most recent list in 2015.

The Federal Railroad Administration (FRA) estimatedthat between 1987 and 1997, an annual average of seven fatalities, fifty-five injuries, 150 evacuations and over $20 million in property damage could have been prevented by PTC. To put this in the context of the entire transportation network, there were 33,782 fatalitieson the road network in 2012.

Although PTC is on NTSB’s “Most Wanted List” and many serious incidents due to human error could be prevented, the monetized safety benefits are significantly less than the costs. The FRA estimates the annual monetary value of the safety benefits from PTC to be about $90 million. The safety benefits may be slightly larger today, considering several serious accidents stemming from a boom in oil shipped via rail.

The costs
The law is an unfunded mandate, which means the costs of meeting the requirements are borne by the railroad operators. The FRA estimatesthat the total capital cost for full PTC deployment according to law would be about $10 billion (about one year’s worth of capital investments for the major U.S. railroads) and annual maintenance costs of $850 million. While this investment might be feasible for major U.S. freight rail companies, local and state governments with tight budgets will have a much more difficult time allocating funds for PTC.

The FRA established an annual $50 million grant program to help support the development of PTC, but the grant has been funded by Congress for only $3 million — well short of the total required cost of $2.75 billion estimatedby the American Public Transportation Association.

Some argue that PTC could be used to optimize business operations with benefits up to $4 billion annually; however, this remains largely speculative.

Regardless of the federal mandate and possible future benefits, the costs of implementing PTC remain a significant barrier.

The systems integration barriers
In addition to costs, PTC has faced barriers in technical implementation, namely system interoperability and allocation of communication spectrum.

Interoperability is key in successful implementation of PTC. In the case of the Northeast Corridor, where the most recent accident occurred, Amtrak operates on both Amtrak-owned track and track owned by regional transit authorities and vice versa. Elsewhere, Amtrak operates on track owned by freight railroads. It is necessary to ensure that the systems developed by the freight railroads, Amtrak and regional authorities all communicate with one another. While interoperable systems have been developed, some issues persist.

Another system integration issue is the acquisition of radio spectrum to support the communication demands of PTC. The Federal Communications Commission (FCC) generally holds auctions for spectrum, but allocates some for emergency services and government agencies.

However, the FCC so far has not addressed the needs of PTC. A consortium of railroad companies exists to purchase appropriate spectrum, but the amount of spectrum and the frequency are still uncertain - especially in highly congested areas in major cities, where choices in spectrum may be scarce. Without guidance from the FCC, obtaining spectrum and ensuring its interoperability is time-consuming and costly.

Going forward
It remains to be seen whether Congress will take immediate action following the Amtrak accident as it did with the 2008 accident in California.

House speaker John Boehner recently said it was “stupid” to claim that the slow rollout of PTC, which may have prevented the accident, is a problem with funding. He may be right that no federal money was cut for rail safety programs, but he also failed to mention that no money was given to help meet the unfunded mandate. Either way, it does not seem likely that local and state governments will receive much help in meeting the unfunded mandate.

Furthermore, a billwas introduced in the Senate this March to extend the PTC deadline to 2020 to help accommodate the cost, interoperability and spectrum barriers the railroads are facing. Perhaps then, the timing of this accident will lead to the failure of the bill and cement the 2015 deadline regardless of the financial and technical barriers.

More information can be found here.

Jeffrey C. Peters is Doctoral Candidate in Energy Economics; Systems Engineer at Purdue University. This storyis published courtesy of The Conversation(under Creative Commons-Attribution/No derivatives.